TILLSON/TOC UPDATE, THURSDAY, DECEMBER 8, 2022

Tomorrow the contractor will be paving approximately 760' of Tillson with temporary asphalt in preparation for winter shut down. This is being done to enhance snow and ice removal efforts for the winter. After paving is finished the one lane configuration will be removed . It is anticipated that all work for this year will be completed by this Friday (12/09/2022) and winter shut down will be in effect. Weather depending work will start back up mid March to early April.