TILLSON/TOC PROGRESS - 5/3 through 5/10

PROGRESS PHOTOS
1. Applying Anti-graffiti product to Walls on Tillson.
2. Vineyard Ave. road construction: Installation of Geotextile Fabric for stabilizing and reinforcing between existing and new road "subbase" soils.
3. Guiderail installation on Tillson and Vineyard.

Scheduled activities for Week of 5/6/24 and this past week's accomplishments:

Note: Toc Dr. and Vineyard Ave. (at Tillson Ave.) are presently closed for ongoing construction. No access to Vineyard Ave. from Tillson Ave.

1. Tillson Ave.: Next week: Curb preparation/placement, and tree/shrub plantings. Preparations for paving and swales. This past week we completed retaining wall by applying anti-graffiti product, reseeded lawn areas, and performed watering of new seed and established grass areas. Guiderail installations occurred.

2. RT 44/55 (Vineyard Ave.): Next week: Continue underdrain, curb preparation/placement and grading of subbase for upcoming paving. This past week we set catch basin and sewer manhole rims and grates, and continued underdrainage. We also continued guiderail installations, and full depth road construction.

3. TOC Drive: Next week: Complete surface drainage and underdrainage and road subbase installation in preparation for paving. This past week we completed excavations for new road, drainage and underdrainage.

Vineyard Ave. will resume being an active construction work zone. Sidewalks will remain closed to pedestrian traffic throughout project completion. For the safety of the residents of the Town of Lloyd, no pedestrian traffic in this work zone is permitted.

If you have any questions and or concerns, please feel free to contact our Resident Engineer, Mr. Peter McCourt through his email address, which is: pmccourt@bartonandloguidice.com.

Note: Adverse weather and/or predicted forecasts, may impact above schedule.
Work schedules noted above, have been per contractor's 2-week schedules provided, and are subject to change.