TILLSON/TOC UPDATE 4/26 THROUGH WEEK OF 4/29

PROGRESS PHOTOS

1. Drainage grates set for paving.

2. Started Guiderails.

Progress made on drainage connections on Vineyard Ave. Guiderails started and will continue the week of 4/29.

Roadwork on Toc Drive at the intersection will continue in preparation for elevation work to prep for paving.

Scheduled activities for Week of 4/29/24 include:

1. Tillson Ave.: Curb Construction.

2. RT 44/55 (Vineyard Ave.): Curb construction.

Vineyard Ave. will resume being an active construction work zone. Sidewalks will remain closed to pedestrian traffic throughout project completion. For the safety of the residents of the Town of Lloyd, no pedestrian traffic in this work zone is permitted.

If you have any questions and or concerns, please feel free to contact our Resident Engineer, Mr. Peter McCourt through his email address, which is: pmccourt@bartonandlogiduice.com.

Note: Adverse weather and/or predicted forecasts, may impact above schedule.

Work schedules noted above, have been per contractor's 2-week schedules provided, and are subject to change.