TILLSON/TOC UPDATE 4/8/2024

TILLSON/TOC UPDATE 4/8/2024

Work will be restarting week of April 8, 2024.

Scheduled activities include:

1. Reestablishing Detour Signage for Toc Dr. and Vineyard Ave. will begin Monday. Contractor will be closing Toc Drive and Vineyard Avenue with reinstallation of all concrete barriers blocking road access as in the past.

2. Tillson Ave.: Site cleanup and re-topsoil from #2 Tillson towards Rt 9W.

3. RT 44/55 (Vineyard Ave.): Remove concrete barrier along creek and site cleanup. Drainage installation on Vineyard from DS 111 to DS 109. This excavation will completely cross Vineyard Ave. approximately 150 ft north of Toc Drive, rendering no access from the main part of Town.

Vineyard Ave. will resume being an active construction work zone. Sidewalks will remain closed to pedestrian traffic throughout project completion. For the safety of the residents of the Town of Lloyd, no pedestrian traffic in this work zone is permitted.

If you have any questions and or concerns, please feel free to contact our Resident Engineer, Mr. Peter McCourt through his email address, which is: pmccourt@bartonandlogiduice.com.

Note: Adverse weather and/or predicted forecasts, may impact above schedule.

Work schedules noted above, have been per contractor's 2-week schedules provided, and are subject to change.