TILLSON\TOC UPDATE WEEK OF 4/19 THROUGH 4/26

TILLSON/TOC UPDATE 4/19/2024

PROGRESS PHOTOS

1. Completing drainage on Vineyard.

2. Seed and Mulch slope to new culvert.

Scheduled activities for Week of 4/22/24 include:

Note: Toc Dr. and Vineyard Ave. (at Tillson Ave.) are presently closed for ongoing construction. No access to Vineyard Ave. from Tillson Ave.

1. Tillson Ave.: Underdrain and grading for curbing to new culvert.

2. RT 44/55 (Vineyard Ave.): Complete drainage installation. Set Utility Castings to grade. Cleanup and Topsoil. Install underdrain and grading for curbing. Remove driveway to #135 Vineyard. Begin installation of guiderails.

Vineyard Ave. will resume being an active construction work zone. Sidewalks will remain closed to pedestrian traffic throughout project completion. For the safety of the residents of the Town of Lloyd, no pedestrian traffic in this work zone is permitted.

If you have any questions and or concerns, please feel free to contact our Resident Engineer, Mr. Peter McCourt through his email address, which is: pmccourt@bartonandlogiduice.com.

Note: Adverse weather and/or predicted forecasts, may impact above schedule.

Work schedules noted above, have been per contractor's 2-week schedules provided, and are subject to change.