TILLSON/TOC UPDATE, THURSDAY, DECEMBER 8, 2022
Tomorrow the contractor will be paving approximately 760' of Tillson with temporary asphalt in preparation for winter shut down. This is... more ››
TILLSON/TOC UPDATE, FRIDAY, NOVEMBER 4, 2022:
Walls continue to be erected and will continue. Two large trees were taken down by a tree service.The plan for next week is to have the... more ››
NYS Department of Public Services Winter Outreach and Education Program
NYS Department of Public Services Winter Outreach and Education Program encourages consumers to take simple, low-cost energy savings... more ››
Tillson/Toc Update, Friday, October 28,2022
The one way from 9W to Vineyard Ave.
TILLSON/TOC UPDATE, FRIDAY, OCTOBER 21, 2022
The ONE WAY from 9W to Vineyard Ave. still remains in place and will for some time.
TILLSON/TOC UPDATE, FRIDAY, OCTOBER 14, 2022
The one way configuration on Tillson from 9W to Vineyard Ave./44-55 will continue. The installation of the retaining walls has begun on the... more ››
TILLSON/TOC UPDATE FRIDAY, OCTOBER 7, 2022
This week the Contractor is placing hot asphalt in the excavated crossings that were done to move utilities locations to the driveways.... more ››
3rd QUARTER 2022 UPDATE FROM SUPERVISOR PLAVCHAK
The 3rd quarter of 2022 started off with a 4th of July Celebration highlighted by an impressive Fireworks display on July 2nd at the Town... more ››
TILLSON/TOC UPDATE: FRIDAY, SEPTEMBER 30, 2022
Work on Tillson Ave. will resume Monday, 10/3/2022 7:00 a.m. Tillson Ave. East Bound Lane will remain closed as work will continue on the... more ››
TILLSON/TOC UPDATE - FRIDAY, SEPTEMBER 23, 2022
The work on Tillson continues with the relocation of water and gas services on the south side of Tillson. The work zone one way... more ››
Tillson Toc Update Thursday, September 15, 2022
Tillson Ave work will start Monday, 9/19/2022 7:00 a.m. Tillson Ave. East Bound Lane will be closed as work will start on the south side... more ››
TILLSON AVENUE UPDATE - Friday, September 2, 2022
Tentatively on September 12th work will start in earnest with water and gas service relocations in the area of house numbers 21, 17, 11... more ››
Tillson/Toc Realignment Project Update 8/22/2022
The Add Alternate funding has finally been approved for the Rte 44/55-Toc Drive-Tillson intersection portion of the Tillson Ave. contract... more ››
Tillson/Toc Realignment Project Update 8/19/22: FYI: Contractor A. Colarusso & Son (ACS) will have a lane closure scheduled for Monday a.m., 8/22/22
Tillson/Toc Realignment Project Update as of 7-20-2022
Test pits to verify utility locations, depths, and conditions will start tomorrow(Thursday July 21, 2022) on Tillson Ave. Work is estimated... more ››
Tillson/Toc Realignment Construction Update: Work Planned through the week ending 07/22/202
Construction utility layout will continue through the end of this week. Work will include the layout and striping of all underground... more ››
2nd Quarter 2022 Update from Supervisor Plavchak
2nd quarter 2022 the Town of Lloyd continues to make progress and move forward.
Southbound UCAT Bus Stop in the Hamlet Has Been Relocated
The southbound UCAT Bus Stop has been relocated from the old bank to the new stop location which is right across the street, on the... more ››
Chief James Janso & the Town of Lloyd Police Department Receive the Seven Seals Award
On Tuesday, June 28, 2022, Chief James Janso & the Town of Lloyd Police Department received the Seven Seals Award. This award is... more ››